#747 – Point Defiance Regional Treatment Retrofit


Project Details
Client:
City of Tacoma
Project Manager:
Bill Parsons
Location:
Tacoma, WA
Value:
$4,638,912
Share:

Project Info

Construct stormwater flow splitter system, conveyance, pretreatment system, concrete cascade pools, distribution troughs, high flow treatment cells, landscaping, and irrigation. Stockpiling approximately 22,000 cy of contaminated soil on site and removing approximately 73,000 cy of clean soil excavation, utility constructing approximately 1,150 lf of storm sewer and the replacement of an existing outfall with a 36″ outfall. Small building demolition/removal including site utility removal, and abandonment.